We started with VALUE. Now it's time to talk about CONST and compare the two keywords: the pros and cons and when you should use each. Even if you always use these keywords, read on. You might be surprised.

 

Let's start with a quick recap of the previous TechTip. In RPG, parameters passed between programs are, by default, passed by reference. In other words, what is passed when program A calls program B are the references to the locations (or addresses) in memory of the parameters used, not the contents of the parameters. However, when you call a procedure or a function, you're allowed to choose how the parameters should be passed.

 

If the keyword VALUE is used in a parameter, then what will happen is that a copy of the parameter's contents will be created in memory and passed to the called program, thus passing its value instead of its reference. In practical terms, this means that whatever changes are made to the parameter in the called procedure won't be reflected in the calling program/procedure. That's the VALUE keyword in a nutshell.

 

CONST, however, works differently. When you use the CONST keyword, the parameter is passed by reference, but (and this is the main advantage) you won't be allowed to change its contents intentionally. The compiler returns a compilation error if your code tries to change the parameter's contents. This may sound a bit confusing, so let's analyze an example:

 

P MyProc         B                   EXPORT

D MyProc         PI             N          

D Parm_A                      10A   VALUE  

D Parm_B                       4P 0 CONST  

                                            

* (...)                                    

                                            

C                   Eval     Parm_A = 'A'  

C                   Eval     Parm_B = 42

 

If you tried to compile this piece of code, the compilation would fail because PARM_B is defined in the procedure interface with the CONST keyword. This means that you cannot change its value directly at compilation time.

 

That's the beauty of CONST: it helps your code speak for itself! If you define a parameter with CONST, what you're really saying is "the contents of this parameter are to remain the same (i.e., constant) throughout the execution of this procedure." Some programmers argue that you should define all your input parameters with CONST: it clearly states that they are input parameters and therefore cannot be changed. I partially agree with this approach, because you cannot intentionally change a variable defined with CONST. You can actually change the contents at runtime, in debug mode. It's any interesting experience; try it! Anyway, note the word intentionally. It's possible to change the contents unintentionally when there's a buffer overflow (caused by poorly managed pointers or bad prototypes declaration) and part of the parameter's content gets overwritten. These situations are extremely difficult to identify and solve.

VALUE Versus CONST

Ok, let's imagine that I change the procedure shown above and remove the line that changes PARM_B. It's now possible to compile and call MyProc. Let's also imagine that I have another program that calls this procedure, like so:

 

C                   CallP     MyProc(Parm_A : Parm_B)

 

No matter what happens in MyProc, the original (in other words, the calling program's) Parm_A variable will never get changed (a bit like "What happens in MyProc stays in MyProc"). Because Parm_A is defined with VALUE in MyProc, what will happen "behind the scenes" is that the system will copy the contents of Parm_A to a new variable and pass that variable's memory address (its pointer) to MyProc. This is important to know, because if Parm_A was a big variablesay, a 16Mb arrayinstead of a simple 10-character string, it would take a bit to duplicate it before MyProc could be called. And this will happen every single time the procedure is called.

 

However, this doesn't happen with Parm_B: its contents are passed by reference and, as I said before, cannot be explicitly changed. (Actually, I said intentionally, but let's go with explicitly now, just for the sake of argument.) Parm_B can be changed in yet another way: if you happen to have a field that has the same name as the parameter. You can argue that this might not happen with a parameter called Parm_B, but just for a moment let's imagine that someone would actually create a field called Parm_B in one of the files used by MyProc. Whenever that new record of that file is read, Parm_B's contents would be implicitly changed. The big problem here is that the changed contents would be passed back to the calling program when the procedure ended. Unlike VALUE, CONST only prevents compile-time changes to the parameter's contents, not run-time changes.

 

Just a quick note regarding variable/parameter naming: you should never use field names as parameter names, and you should also use prefixes for files used in a procedure or program! I'll go over a bunch of ground rules later in this series, with a TechTip exclusively dedicated to good naming conventions and practices.

So What Keyword Should I Use for My Input Parameters?

As you can see, both keywords have pros and cons. You need to be careful when defining your procedure's parameters, taking into account the what the parameters' sizes are, what you're going to do with them and, if you know in advance, how often will the procedure get called.

 

VALUE is nice because you're 100% sure (unless something really, really weird happens) that the original variable is not changed. However, it's not a good idea to use this keyword in intensively used procedures or big parameters because the system will have to copy the parameter's contents to a new variable every single time the procedure is called.

 

CONST is also nice because, since there's no content copying, the procedure gets called immediately regardless of the size of the parameters; only the pointers are passed. It's faster and also "cleaner" in the sense that you're not allowed to intentionally change the parameter's contents. Just use proper naming and be careful with the prototype definitions! You will be able to avoid those nasty buffer overflow and I/O nightmares I mentioned previously.

 

As usual, your feedback is most welcome! I try to incorporate as much reader feedback as possible into my articles (Sébastien, Jared, and Chris, this is for you this time) because I humbly believe that there's always room for improvement and that everyone can learn from each other every day.

 

The next TechTip will continue to discuss parameters, covering the OPTIONS keyword and all that is associated with it. Until next time!

BLOG COMMENTS POWERED BY DISQUS

LATEST COMMENTS

Support MC Press Online

$

Book Reviews

Resource Center

  • SB Profound WC 5536 Have you been wondering about Node.js? Our free Node.js Webinar Series takes you from total beginner to creating a fully-functional IBM i Node.js business application. You can find Part 1 here. In Part 2 of our free Node.js Webinar Series, Brian May teaches you the different tooling options available for writing code, debugging, and using Git for version control. Brian will briefly discuss the different tools available, and demonstrate his preferred setup for Node development on IBM i or any platform. Attend this webinar to learn:

  • SB Profound WP 5539More than ever, there is a demand for IT to deliver innovation. Your IBM i has been an essential part of your business operations for years. However, your organization may struggle to maintain the current system and implement new projects. The thousands of customers we've worked with and surveyed state that expectations regarding the digital footprint and vision of the company are not aligned with the current IT environment.

  • SB HelpSystems ROBOT Generic IBM announced the E1080 servers using the latest Power10 processor in September 2021. The most powerful processor from IBM to date, Power10 is designed to handle the demands of doing business in today’s high-tech atmosphere, including running cloud applications, supporting big data, and managing AI workloads. But what does Power10 mean for your data center? In this recorded webinar, IBMers Dan Sundt and Dylan Boday join IBM Power Champion Tom Huntington for a discussion on why Power10 technology is the right strategic investment if you run IBM i, AIX, or Linux. In this action-packed hour, Tom will share trends from the IBM i and AIX user communities while Dan and Dylan dive into the tech specs for key hardware, including:

  • Magic MarkTRY the one package that solves all your document design and printing challenges on all your platforms. Produce bar code labels, electronic forms, ad hoc reports, and RFID tags – without programming! MarkMagic is the only document design and print solution that combines report writing, WYSIWYG label and forms design, and conditional printing in one integrated product. Make sure your data survives when catastrophe hits. Request your trial now!  Request Now.

  • SB HelpSystems ROBOT GenericForms of ransomware has been around for over 30 years, and with more and more organizations suffering attacks each year, it continues to endure. What has made ransomware such a durable threat and what is the best way to combat it? In order to prevent ransomware, organizations must first understand how it works.

  • SB HelpSystems ROBOT GenericIT security is a top priority for businesses around the world, but most IBM i pros don’t know where to begin—and most cybersecurity experts don’t know IBM i. In this session, Robin Tatam explores the business impact of lax IBM i security, the top vulnerabilities putting IBM i at risk, and the steps you can take to protect your organization. If you’re looking to avoid unexpected downtime or corrupted data, you don’t want to miss this session.

  • SB HelpSystems ROBOT GenericCan you trust all of your users all of the time? A typical end user receives 16 malicious emails each month, but only 17 percent of these phishing campaigns are reported to IT. Once an attack is underway, most organizations won’t discover the breach until six months later. A staggering amount of damage can occur in that time. Despite these risks, 93 percent of organizations are leaving their IBM i systems vulnerable to cybercrime. In this on-demand webinar, IBM i security experts Robin Tatam and Sandi Moore will reveal:

  • FORTRA Disaster protection is vital to every business. Yet, it often consists of patched together procedures that are prone to error. From automatic backups to data encryption to media management, Robot automates the routine (yet often complex) tasks of iSeries backup and recovery, saving you time and money and making the process safer and more reliable. Automate your backups with the Robot Backup and Recovery Solution. Key features include:

  • FORTRAManaging messages on your IBM i can be more than a full-time job if you have to do it manually. Messages need a response and resources must be monitored—often over multiple systems and across platforms. How can you be sure you won’t miss important system events? Automate your message center with the Robot Message Management Solution. Key features include:

  • FORTRAThe thought of printing, distributing, and storing iSeries reports manually may reduce you to tears. Paper and labor costs associated with report generation can spiral out of control. Mountains of paper threaten to swamp your files. Robot automates report bursting, distribution, bundling, and archiving, and offers secure, selective online report viewing. Manage your reports with the Robot Report Management Solution. Key features include:

  • FORTRAFor over 30 years, Robot has been a leader in systems management for IBM i. With batch job creation and scheduling at its core, the Robot Job Scheduling Solution reduces the opportunity for human error and helps you maintain service levels, automating even the biggest, most complex runbooks. Manage your job schedule with the Robot Job Scheduling Solution. Key features include:

  • LANSA Business users want new applications now. Market and regulatory pressures require faster application updates and delivery into production. Your IBM i developers may be approaching retirement, and you see no sure way to fill their positions with experienced developers. In addition, you may be caught between maintaining your existing applications and the uncertainty of moving to something new.

  • LANSAWhen it comes to creating your business applications, there are hundreds of coding platforms and programming languages to choose from. These options range from very complex traditional programming languages to Low-Code platforms where sometimes no traditional coding experience is needed. Download our whitepaper, The Power of Writing Code in a Low-Code Solution, and:

  • LANSASupply Chain is becoming increasingly complex and unpredictable. From raw materials for manufacturing to food supply chains, the journey from source to production to delivery to consumers is marred with inefficiencies, manual processes, shortages, recalls, counterfeits, and scandals. In this webinar, we discuss how:

  • The MC Resource Centers bring you the widest selection of white papers, trial software, and on-demand webcasts for you to choose from. >> Review the list of White Papers, Trial Software or On-Demand Webcast at the MC Press Resource Center. >> Add the items to yru Cart and complet he checkout process and submit

  • Profound Logic Have you been wondering about Node.js? Our free Node.js Webinar Series takes you from total beginner to creating a fully-functional IBM i Node.js business application.

  • SB Profound WC 5536Join us for this hour-long webcast that will explore:

  • Fortra IT managers hoping to find new IBM i talent are discovering that the pool of experienced RPG programmers and operators or administrators with intimate knowledge of the operating system and the applications that run on it is small. This begs the question: How will you manage the platform that supports such a big part of your business? This guide offers strategies and software suggestions to help you plan IT staffing and resources and smooth the transition after your AS/400 talent retires. Read on to learn: